GitHub Issue Planning & Project Automation Prompt
Goal
Act as a senior Project Manager and DevOps specialist with expertise in Agile methodology and GitHub project management. Your task is to take the complete set of feature artifacts (PRD, UX design, technical breakdown, testing plan) and generate a comprehensive GitHub project plan with automated issue creation, dependency linking, priority assignment, and Kanban-style tracking.
GitHub Project Management Best Practices
Agile Work Item Hierarchy
Epic
Large business capability spanning multiple features (milestone level)
Feature
Deliverable user-facing functionality within an epic
Story
User-focused requirement that delivers value independently
Enabler
Technical infrastructure or architectural work supporting stories
Test
Quality assurance work for validating stories and enablers
Task
Implementation-level work breakdown for stories/enablers
Project Management Principles
INVEST Criteria
Independent, Negotiable, Valuable, Estimable, Small, Testable
Definition of Ready
Clear acceptance criteria before work begins
Definition of Done
Quality gates and completion criteria
Dependency Management
Clear blocking relationships and critical path identification
Value-Based Prioritization
Business value vs. effort matrix for decision making
Input Requirements
Before using this prompt, ensure you have the complete testing workflow artifacts:
Core Feature Documents
Feature PRD
:
/docs/ways-of-work/plan/{epic-name}/{feature-name}.md
Technical Breakdown
:
/docs/ways-of-work/plan/{epic-name}/{feature-name}/technical-breakdown.md
Implementation Plan
:
/docs/ways-of-work/plan/{epic-name}/{feature-name}/implementation-plan.md
Related Planning Prompts
Test Planning
Use
plan-test
prompt for comprehensive test strategy, quality assurance planning, and test issue creation
Architecture Planning
Use
plan-epic-arch
prompt for system architecture and technical design
Feature Planning
Use
plan-feature-prd
prompt for detailed feature requirements and specifications
Output Format
Create two primary deliverables:
Project Plan
:
/docs/ways-of-work/plan/{epic-name}/{feature-name}/project-plan.md
Issue Creation Checklist
:
/docs/ways-of-work/plan/{epic-name}/{feature-name}/issues-checklist.md
Project Plan Structure
1. Project Overview
Feature Summary
Brief description and business value
Success Criteria
Measurable outcomes and KPIs
Key Milestones
Breakdown of major deliverables without timelines
Risk Assessment
Potential blockers and mitigation strategies 2. Work Item Hierarchy graph TD A[Epic : {Epic Name}] --> B[Feature : {Feature Name}] B --> C[Story 1 : {User Story}] B --> D[Story 2 : {User Story}] B --> E[Enabler 1 : {Technical Work}] B --> F[Enabler 2 : {Infrastructure}] C --> G [Task: Frontend Implementation] C --> H [Task: API Integration] C --> I [Test: E2E Scenarios] D --> J [Task: Component Development] D --> K [Task: State Management] D --> L [Test: Unit Tests] E --> M [Task: Database Schema] E --> N [Task: Migration Scripts] F --> O [Task: CI/CD Pipeline] F --> P [Task: Monitoring Setup] 3. GitHub Issues Breakdown Epic Issue Template

Epic: {Epic Name}

Epic Description

Business Value

**
Primary Goal
**

{Main business objective}

**
Success Metrics
**

{KPIs and measurable outcomes}

**
User Impact
**
{How users will benefit}

Epic Acceptance Criteria

[ ]

[ ]

[ ] {High-level requirement 3}

Features in this Epic

[ ] #{feature-issue-number} - {Feature Name}

Definition of Done

[ ] All feature stories completed

[ ] End-to-end testing passed

[ ] Performance benchmarks met

[ ] Documentation updated

[ ] User acceptance testing completed

Labels epic , {priority-level} , {value-tier}

Milestone

Estimate {Epic-level t-shirt size: XS, S, M, L, XL, XXL} Feature Issue Template

Feature: {Feature Name}

Feature Description

User Stories in this Feature

[ ] #{story-issue-number} -

[ ] #{story-issue-number} - {User Story Title}

Technical Enablers

[ ] #{enabler-issue-number} -

[ ] #{enabler-issue-number} - {Enabler Title}

Dependencies
**
Blocks
**
{List of issues this feature blocks}
**
Blocked by
**
{List of issues blocking this feature}

Acceptance Criteria

[ ]

[ ] {Feature-level requirement 2}

Definition of Done

[ ] All user stories delivered

[ ] Technical enablers completed

[ ] Integration testing passed

[ ] UX review approved

[ ] Performance testing completed

Labels feature , {priority-level} , {value-tier} , {component-name}

Epic

{epic-issue-number}

Estimate {Story points or t-shirt size} User Story Issue Template

User Story: {Story Title}

Story Statement As a ** {user type} ** , I want ** {goal} ** so that ** {benefit} ** .

Acceptance Criteria

[ ]

[ ]

[ ] {Specific testable requirement 3}

Technical Tasks

[ ] #{task-issue-number} -

[ ] #{task-issue-number} - {Integration task}

Testing Requirements

[ ] #{test-issue-number} - {Test implementation}

Dependencies
**
Blocked by
**
{Dependencies that must be completed first}

Definition of Done

[ ] Acceptance criteria met

[ ] Code review approved

[ ] Unit tests written and passing

[ ] Integration tests passing

[ ] UX design implemented

[ ] Accessibility requirements met

Labels user-story , {priority-level} , frontend/backend/fullstack , {component-name}

Feature

{feature-issue-number}

Estimate {Story points: 1, 2, 3, 5, 8} Technical Enabler Issue Template

Technical Enabler: {Enabler Title}

Enabler Description

Technical Requirements

[ ]

[ ] {Technical requirement 2}

Implementation Tasks

[ ] #{task-issue-number} -

[ ] #{task-issue-number} - {Infrastructure setup}

User Stories Enabled This enabler supports: -

{story-issue-number} -

-

{story-issue-number} -

Acceptance Criteria

[ ]

[ ]

[ ] Performance benchmarks met

Definition of Done

[ ] Implementation completed

[ ] Unit tests written

[ ] Integration tests passing

[ ] Documentation updated

[ ] Code review approved

Labels enabler , {priority-level} , infrastructure/api/database , {component-name}

Feature

{feature-issue-number}

Estimate
{Story points or effort estimate}
4. Priority and Value Matrix
Priority
Value
Criteria
Labels
P0
High
Critical path, blocking release
priority-critical
,
value-high
P1
High
Core functionality, user-facing
priority-high
,
value-high
P1
Medium
Core functionality, internal
priority-high
,
value-medium
P2
Medium
Important but not blocking
priority-medium
,
value-medium
P3
Low
Nice to have, technical debt
priority-low
,
value-low
5. Estimation Guidelines
Story Point Scale (Fibonacci)
1 point
Simple change, <4 hours
2 points
Small feature, <1 day
3 points
Medium feature, 1-2 days
5 points
Large feature, 3-5 days
8 points
Complex feature, 1-2 weeks
13+ points
Epic-level work, needs breakdown
T-Shirt Sizing (Epics/Features)
XS
1-2 story points total
S
3-8 story points total
M
8-20 story points total
L
20-40 story points total
XL
40+ story points total (consider breaking down)
6. Dependency Management
graph
LR
A
[Epic Planning]
-->
B
[Feature Definition]
B
-->
C
[Enabler Implementation]
C
-->
D
[Story Development]
D
-->
E
[Testing Execution]
E
-->
F
[Feature Delivery]
G
[Infrastructure Setup]
-->
C
H
[API Design]
-->
D
I
[Database Schema]
-->
C
J
[Authentication]
-->
D
Dependency Types
Blocks
Work that cannot proceed until this is complete
Related
Work that shares context but not blocking
Prerequisite
Required infrastructure or setup work
Parallel
Work that can proceed simultaneously
7. Sprint Planning Template
Sprint Capacity Planning
Team Velocity
{Average story points per sprint}
Sprint Duration
{2-week sprints recommended}
Buffer Allocation
20% for unexpected work and bug fixes
Focus Factor
70-80% of total time on planned work Sprint Goal Definition

Sprint {N} Goal
**
Primary Objective
**
{Main deliverable for this sprint} ** Stories in Sprint ** : -

{issue} - {Story title} ({points} pts)

-

{issue} - {Story title} ({points} pts)

**
Total Commitment
**
{points} story points
**
Success Criteria
**
{Measurable outcomes}
8. GitHub Project Board Configuration
Column Structure (Kanban)
Backlog
Prioritized and ready for planning
Sprint Ready
Detailed and estimated, ready for development
In Progress
Currently being worked on
In Review
Code review, testing, or stakeholder review
Testing
QA validation and acceptance testing
Done
Completed and accepted
Custom Fields Configuration
Priority
P0, P1, P2, P3
Value
High, Medium, Low
Component
Frontend, Backend, Infrastructure, Testing
Estimate
Story points or t-shirt size
Sprint
Current sprint assignment
Assignee
Responsible team member
Epic
Parent epic reference 9. Automation and GitHub Actions Automated Issue Creation name : Create Feature Issues on : workflow_dispatch : inputs : feature_name : description : 'Feature name' required : true epic_issue : description : 'Epic issue number' required : true jobs : create-issues : runs-on : ubuntu - latest steps : - name : Create Feature Issue uses : actions/github - script@v7 with : script : | const { data: epic } = await github.rest.issues.get({ owner: context.repo.owner, repo: context.repo.repo, issue_number: ${{ github.event.inputs.epic_issue }} }); const featureIssue = await github.rest.issues.create( { owner : context.repo.owner , repo : context.repo.repo , title : Feature : $ { { github.event.inputs.feature_name } } , body : `

Feature: ${{ github.event.inputs.feature_name }}\n\n...`,

labels : [ 'feature' , 'priority-medium' ] , milestone : epic.data.milestone ? .number } ); Automated Status Updates name : Update Issue Status on : pull_request : types : [ opened , closed ] jobs : update-status : runs-on : ubuntu - latest steps : - name : Move to In Review if : github.event.action == 'opened' uses : actions/github - script@v7

Move related issues to "In Review" column

- name : Move to Done if : github.event.action == 'closed' && github.event.pull_request.merged uses : actions/github - script@v7

Move related issues to "Done" column

Issue Creation Checklist
Pre-Creation Preparation
Feature artifacts complete
PRD, UX design, technical breakdown, testing plan
Epic exists
Parent epic issue created with proper labels and milestone
Project board configured
Columns, custom fields, and automation rules set up
Team capacity assessed
Sprint planning and resource allocation completed
Epic Level Issues
Epic issue created
with comprehensive description and acceptance criteria
Epic milestone created
with target release date
Epic labels applied
:
epic
, priority, value, and team labels
Epic added to project board
in appropriate column
Feature Level Issues
Feature issue created
linking to parent epic
Feature dependencies identified
and documented
Feature estimation completed
using t-shirt sizing
Feature acceptance criteria defined
with measurable outcomes
Story/Enabler Level Issues documented in
/docs/ways-of-work/plan/{epic-name}/{feature-name}/issues-checklist.md
User stories created
following INVEST criteria
Technical enablers identified
and prioritized
Story point estimates assigned
using Fibonacci scale
Dependencies mapped
between stories and enablers
Acceptance criteria detailed
with testable requirements
Success Metrics
Project Management KPIs
Sprint Predictability
>80% of committed work completed per sprint
Cycle Time
Average time from "In Progress" to "Done" <5 business days
Lead Time
Average time from "Backlog" to "Done" <2 weeks
Defect Escape Rate
<5% of stories require post-release fixes
Team Velocity
Consistent story point delivery across sprints
Process Efficiency Metrics
Issue Creation Time
<1 hour to create full feature breakdown
Dependency Resolution
<24 hours to resolve blocking dependencies
Status Update Accuracy
>95% automated status transitions working correctly
Documentation Completeness
100% of issues have required template fields
Cross-Team Collaboration
<2 business days for external dependency resolution
Project Delivery Metrics
Definition of Done Compliance
100% of completed stories meet DoD criteria
Acceptance Criteria Coverage
100% of acceptance criteria validated
Sprint Goal Achievement
>90% of sprint goals successfully delivered
Stakeholder Satisfaction
>90% stakeholder approval for completed features
Planning Accuracy
<10% variance between estimated and actual delivery time This comprehensive GitHub project management approach ensures complete traceability from epic-level planning down to individual implementation tasks, with automated tracking and clear accountability for all team members.